A building has a design case energy use of 463,222 kWh/yr. What minimum purchase

[复制链接]

1759

主题

1

好友

5680

积分

管理员

Rank: 9Rank: 9Rank: 9

跳转到指定楼层
楼主
发表于 2012-8-12 18:42:55 |只看该作者 |倒序浏览
试卷: LEED AP BD+C模拟题B[查看]
A building has a design case energy use of 463,222 kWh/yr. What minimum purchase from
a wind supplier would be needed to earn a project 2 points?
A: 324,255 kWh
B: 162,127 kWh
C: 463,222 kWh
D: 926,444 kWh

参考答案: A

本题解释:
Notes:
Green Power requires 35% green power for a two year contract to earn two points.
The formula for green power is:
kWh/yr X 35% X 2 years = total kWh to purchase
463,222 kWh/yr X 35% X 2 years = 324,255 kWh to purchase
分享到: QQ空间QQ空间 腾讯微博腾讯微博 腾讯朋友腾讯朋友
分享分享0 收藏收藏0
回复

使用道具 举报

您需要登录后才可以回帖 登录 | 立即注册

关闭

站长推荐上一条 /1 下一条

Archiver|手机版|LEED GA/LEED AP考试学习平台|版权所有|备案号(沪ICP备11019119号-2)|leedgap   

GMT+8, 2025-4-21 07:27 , Processed in 0.078466 second(s), 25 queries .

Powered by Discuz! X2.5 & Exam 1.4

© 2001-2012 Comsenz Inc.

回顶部