An apartment complex is being built in a suburban area on a Greenfield site. The site has
an existing imperviousness of 25%. The pre-development discharge volume of
stormwater is 8,000 gallons. What can the maximum post-development discharge volume
be to qualify for Sustainable Sites Credit, Stormwater Design-Quantity Control?
A: 10,000 gallons
B: 4,000 gallons
C: 6,000 gallons
D: 2,000 gallons
E: 8,000 gallons

参考答案: E

本题解释:
Notes:
Note that the question specifically asks for the maximum post-development discharge
volume.
The Greenfield site has an existing imperviousness that is less than or equal to 50%. The
post-development peak discharge rate and the quantity must not exceed the
pre-development peak discharge rate and quantity to meet the requirements of
Sustainable Sites Credit, Stormwater Design-Quantity Control, Option 1. The question
gave a pre-development discharge rate of 8,000 gallons. The post-development
discharge rate would have to be the same or less than this pre-development discharge
rate.
Another option, not discussed in this question, is to implement a stormwater management
plan that protects receiving stream channels from excessive erosion by implementing a
stream channel protection strategy and quantity control strategies.
分享到: QQ空间QQ空间 腾讯微博腾讯微博 腾讯朋友腾讯朋友
分享分享0 收藏收藏0
回复

使用道具 举报

您需要登录后才可以回帖 登录 | 立即注册

关闭

站长推荐上一条 /1 下一条

Archiver|手机版|LEED GA/LEED AP考试学习平台|版权所有|备案号(沪ICP备11019119号-2)|leedgap   

GMT+8, 2024-12-26 22:02 , Processed in 0.074303 second(s), 25 queries .

Powered by Discuz! X2.5 & Exam 1.4

© 2001-2012 Comsenz Inc.

回顶部