试卷: LEED AP BD+C模拟题D[查看] A 5 story office building is being constructed on the site of an old warehouse. The site has a zero-lot-line and is completely paved with non-porous pavement. The pre-development discharge volume of stormwater is 10,000 gallons. What post-development discharge volume would qualify for Sustainable Sites Credit, Stormwater Design-Quantity Control? A: 8,000 gallons, or less B: 10,000 gallons, or less C: 5,000 gallons, or less D: 7,500 gallons, or less 参考答案: D
本题解释: Notes:
The site has an imperviousness greater than 50% because it is completely paved, so
Option 2 must be met for the requirements. A stormwater management plan must have a
25% decrease in volume. The pre-development discharge rate is 10,000 gallons, so the
post-development discharge rate must be 7,500 gallons or less (25% less than 10,000
gallons). |
|