LEED GAP

 找回密码
 立即注册

QQ登录

只需一步,快速开始

搜索
查看: 277|回复: 0
打印 上一主题 下一主题

A CxA has arrived on a project site to verify the installation and performance o

[复制链接]

1759

主题

1

好友

5674

积分

管理员

Rank: 9Rank: 9Rank: 9

跳转到指定楼层
楼主
发表于 2012-8-12 18:42:55 |只看该作者 |倒序浏览
试卷: LEED AP BD+C模拟题C[查看]
A CxA has arrived on a project site to verify the installation and performance of the systems as part of fundamental commissioning. Which
of the following are not typical steps the CxA will perform?
A: Functional performance testing
B: Prefunctional inspections
C: Comparing results with the owner’s project requirements
D: Training operating personnel

参考答案: D

本题解释:
Notes:
Reference: Energy and Atmosphere Prerequisite, Fundamental Commissioning of Building Energy Systems,
Not the question uses the word NOT.
When verifying the installation and performance of commissioned systems, three steps are typical.

1. Installation inspections
2. System performance testing
3. Comparison of the results to the original requirements
分享到: QQ空间QQ空间 腾讯微博腾讯微博 腾讯朋友腾讯朋友
分享分享0 收藏收藏0
回复

使用道具 举报

您需要登录后才可以回帖 登录 | 立即注册

关闭

站长推荐上一条 /1 下一条

Archiver|手机版|LEED GA/LEED AP考试学习平台|版权所有|备案号(沪ICP备11019119号-2)|leedgap   

GMT+8, 2024-12-26 10:25 , Processed in 0.075180 second(s), 25 queries .

Powered by Discuz! X2.5 & Exam 1.4

© 2001-2012 Comsenz Inc.

回顶部