A project space is 45,000 sq. ft. A project team has selected a commissioning ag

[复制链接]

262

主题

0

好友

33

积分

管理员

Rank: 9Rank: 9Rank: 9

跳转到指定楼层
楼主
发表于 2012-8-12 17:49:01 |只看该作者 |倒序浏览
试卷: LEED AP ID+C 模拟试卷B[查看]
A project space is 45,000 sq. ft. A project team has selected a commissioning agent who is a construction manager not holding any construction contracts. What will the agent not need to do for fundamental commissioning?
A: Define a baseline to be used for specifying whole-building or equipment specific compliance with energy codes or standards
B: Review results of system performance verification
C: Coordinate commissioning testing
D: Direct the commissioning team and the process

参考答案: A

本题解释:
Reference: Energy and Atmosphere Credit, Measurement and Verification, Implementation, Step 2

Defining a baseline to be used for specifying whole-building or equipment specific compliance with energy codes or standards is part of an M&V plan, not part of commissioning.


分享到: QQ空间QQ空间 腾讯微博腾讯微博 腾讯朋友腾讯朋友
分享分享0 收藏收藏0
回复

使用道具 举报

您需要登录后才可以回帖 登录 | 立即注册

关闭

站长推荐上一条 /1 下一条

Archiver|手机版|LEED GA/LEED AP考试学习平台|版权所有|备案号(沪ICP备11019119号-2)|leedgap   

GMT+8, 2024-12-26 11:00 , Processed in 0.075145 second(s), 25 queries .

Powered by Discuz! X2.5 & Exam 1.4

© 2001-2012 Comsenz Inc.

回顶部