试卷: LEED AP BD+C模拟题A[查看] A project team is reviewing strategies for retaining stormwater on site for a project that will have a
large amount of open space with turf grass. Which strategies will help with retaining stormwater
on-site?(choose 3) A: Installing cisterns to capture stormwater for irrigation B: Building a constructed wetland C: Placing mulch around the areas of turf grass D: Installing bioswales E: Increasing the efficiency of the irrigation system 参考答案: ABD
本题解释: Notes:
Reference: Sustainable Sites Credit, Stormwater Design-Quantity Control, Examples
Keeping stormwater onsite can be done with ponds, wetlands, retention ponds, vegetated filter
strips, rain gardens, storing the water onsite for later use, etc. |
|