A project team working a new construction project is attempting to divert construction waste from
the landfill. Total construction waste is estimated to be 257 tons. What is the minimum number of
tons that need to be diverted to earn exemplary performance for Materials and Resources Credit,
Construction Waste Management?
A: 245 tons
B: 218 tons
C: 257 tons
D: 193 tons

参考答案: A

本题解释:
Notes:


To earn exemplary performance for MR Credit 2, a project must divert 95% or more of total
construction waste.


If there is a total of 257 of construction waste, so 257*.95 = 244.15, round up


257 would also meet the requirement, but the question asks for the minimum number of tons, so
245 is the best choice.
分享到: QQ空间QQ空间 腾讯微博腾讯微博 腾讯朋友腾讯朋友
分享分享0 收藏收藏0
回复

使用道具 举报

您需要登录后才可以回帖 登录 | 立即注册

关闭

站长推荐上一条 /1 下一条

Archiver|手机版|LEED GA/LEED AP考试学习平台|版权所有|备案号(沪ICP备11019119号-2)|leedgap   

GMT+8, 2024-12-25 23:56 , Processed in 0.080518 second(s), 25 queries .

Powered by Discuz! X2.5 & Exam 1.4

© 2001-2012 Comsenz Inc.

回顶部