LEED GAP

 找回密码
 立即注册

QQ登录

只需一步,快速开始

搜索
查看: 392|回复: 0
打印 上一主题 下一主题

A CxA has been selected who is a subcontractor of the general contractor with co

[复制链接]

1759

主题

1

好友

5680

积分

管理员

Rank: 9Rank: 9Rank: 9

跳转到指定楼层
楼主
发表于 2012-8-12 16:22:18 |只看该作者 |倒序浏览
试卷: LEED AP BD+C模拟题A[查看]
A CxA has been selected who is a subcontractor of the general contractor with construction
responsibilities. What tasks does the CxA not need to perform for fundamental commissioning?
A: Complete a summary commissioning report
B: Review the basis of design
C: Develop and incorporate commissioning requirements into the construction documents
D: Develop a systems manual

参考答案: D

本题解释:
Notes:
Reference: Energy and Atmosphere Prerequisite, Fundamental Commissioning of Building Energy
Systems , Requirements
There are six activities that must be completed by the project team for Fundamental
Commissioning.
1. Designate an individual as the commissioning authority (CxA) to lead, review and oversee the
completion of the commissioning process activities.
2. The owner must document the owner\'s project requirements. The design team must develop the
basis of design. The CxA must review these documents for clarity and completeness. The owner
and design team must be responsible for updates to their respective documents.
3. Develop and incorporate commissioning requirements into the construction documents.
4. Develop and implement a commissioning plan.
5. Verify the installation and performance of the systems to be commissioned.
6. Complete a summary commissioning report.
A systems manual is part of Enhanced Commissioning, not Fundamental Commissioning.
分享到: QQ空间QQ空间 腾讯微博腾讯微博 腾讯朋友腾讯朋友
分享分享0 收藏收藏0
回复

使用道具 举报

您需要登录后才可以回帖 登录 | 立即注册

关闭

站长推荐上一条 /1 下一条

Archiver|手机版|LEED GA/LEED AP考试学习平台|版权所有|备案号(沪ICP备11019119号-2)|leedgap   

GMT+8, 2025-4-20 15:09 , Processed in 0.075591 second(s), 25 queries .

Powered by Discuz! X2.5 & Exam 1.4

© 2001-2012 Comsenz Inc.

回顶部