In a condominium project, what requirements must be met for ETS control if the h

[复制链接]

1759

主题

1

好友

5674

积分

管理员

Rank: 9Rank: 9Rank: 9

跳转到指定楼层
楼主
发表于 2012-8-10 16:15:43 |只看该作者 |倒序浏览
试卷: LEED AP BD+C模拟题A[查看]
In a condominium project, what requirements must be met for ETS control if the hallways and
rooms have the same air pressure?
A: Locate all exterior smoking areas 20 feet away from any outdoor air intakes
B: Use MERV 13 filters on all vents to common areas
C: Weatherstrip all doors leading to common hallways
D: Meet the requirements of ASHRAE 62.1-2007

参考答案: C

本题解释:
Notes:


Reference: Indoor Environmental Quality Prerequisite, Environmental Tobacco Smoke (ETS)
Control


For residential projects Case 2 must be followed.
If the same air pressure exists between the units and the hallways, the pathways between the units
must be sealed to prevent ETS transfer.


Note that Case 2 does not require a negative pressure differential for each unit, only that the unit
does not leak too much air.

分享到: QQ空间QQ空间 腾讯微博腾讯微博 腾讯朋友腾讯朋友
分享分享0 收藏收藏0
回复

使用道具 举报

您需要登录后才可以回帖 登录 | 立即注册

关闭

站长推荐上一条 /1 下一条

Archiver|手机版|LEED GA/LEED AP考试学习平台|版权所有|备案号(沪ICP备11019119号-2)|leedgap   

GMT+8, 2024-12-23 11:36 , Processed in 0.073988 second(s), 25 queries .

Powered by Discuz! X2.5 & Exam 1.4

© 2001-2012 Comsenz Inc.

回顶部