试卷: LEED v4 GA模拟题B卷中文[查看] 项目位于一个有需求响应程序的地方(Demand-response Program),并且有足够的空间安放风力涡轮机考虑到现场可再生能源使用。如果项目实施这两种策略,下列哪种情况会发生?A project is located in an area with a demand-response program and that has enough room for a wind-turbine to allow for on-site renewable energy. If the project implements both of these strategies, which of the following will occur? A: 项目的可再生能源发电将减少 The project’s renewable energy production will decrease B: 项目最低能效表现(Minimum Energy Performance)将减少 The project’s minimum energy performance will decrease C: 项目的能源需求将减少 The project’s energy demands will decrease D: 项目的能源费用将减少 The project’s energy costs will decrease 参考答案: D
本题解释: 正确答案:D
系统解析: A:如果项目有需求响应程序,可再生能源发电并不会减少。
B:项目最低能效表现保持不变,因为现场可再生能源对减少最低能效表现并不能贡献,但对优化能效表现能贡献。
C:项目的用能需求保持不变。风力涡轮机会偿一部分电网供电。
正确答案:D:Demand-response programs usually include financial incentives during demand response events. The utility company asks the building to use less electricity, the building agrees, and the building owner is rewarded with a price break. In turn, the utility company saves money by spending less money on additional transmission lines and power plants.
A:The renewable energy production doesn’t decrease if the project is also in a demand-response program.
B:The minimum energy performance for the project would remain the same. On-site renewables do not count toward reducing the minimum energy required to run the building.
C:The energy demands remain constant for this project. The wind turbine will offset the need for grid-supplied energy. The demand response participation will curb the building’s energy use during peak times.
|
|