A project team will try to earn Construction Indoor Air Quality Management Plan, During Construction and Construction Indoor Air Quality Management Plan, Before Occupancy. The building will have permanently installed air handlers and will use air quality testing before occupancy. What must be done to achieve these credits?
A: Meet the SMACNA IAQ guidelines after construction and before occupancy
B: Prior to occupancy, perform a building flush-out that supplies a total air volume of 14,000 cu. ft. of outdoor air per sq. ft
C: Conduct all air measurements once the building is occupied and running normally
D: Complete an IAQ management plan

参考答案: D

本题解释:
Reference: Indoor Environmental Quality Credit, Construction Indoor Air Quality Management Plan

The first step for these credits is completing the construction IAQ management plan. Once the plan is complete the baseline IAQ test will confirm if the contaminant levels are acceptable before occupancy.

A building flush-out does not have to be performed. The flush-out is 1 of 2 options, and the question states Option 2, Air Quality Testing will be done.

SMACNA IAQ guidelines must be met During Construction, not Before Occupancy (hence the standard name - SMACNA IAQ Guidelines for Occupied Buildings UNDER CONSTRUCTION).

Air measurements must be taken with the building is running under normal operations, but prior to occupancy.

分享到: QQ空间QQ空间 腾讯微博腾讯微博 腾讯朋友腾讯朋友
分享分享0 收藏收藏0
回复

使用道具 举报

您需要登录后才可以回帖 登录 | 立即注册

关闭

站长推荐上一条 /1 下一条

Archiver|手机版|LEED GA/LEED AP考试学习平台|版权所有|备案号(沪ICP备11019119号-2)|leedgap   

GMT+8, 2024-12-23 23:03 , Processed in 0.081264 second(s), 25 queries .

Powered by Discuz! X2.5 & Exam 1.4

© 2001-2012 Comsenz Inc.

回顶部