试卷: LEED AP ID+C 模拟试卷C[查看] A project team will try to earn Construction Indoor Air Quality Management Plan, During Construction and Construction Indoor Air Quality Management Plan, Before Occupancy. The building will have permanently installed air handlers and will use air quality testing before occupancy.
What must be done to achieve these credits?
A: Meet the SMACNA IAQ guidelines after construction and before occupancy B: Prior to occupancy, perform a building flush-out that supplies a total air volume of 14,000 cu. ft. of outdoor air per sq. ft C: Conduct all air measurements once the building is occupied and running normally D: Complete an IAQ management plan 参考答案: D
本题解释: Reference: Indoor Environmental Quality Credit, Construction Indoor Air Quality Management Plan
The first step for these credits is completing the construction IAQ management plan. Once the plan is complete the baseline IAQ test will confirm if the contaminant levels are acceptable before occupancy.
A building flush-out does not have to be performed. The flush-out is 1 of 2 options, and the question states Option 2, Air Quality Testing will be done.
SMACNA IAQ guidelines must be met During Construction, not Before Occupancy (hence the standard name - SMACNA IAQ Guidelines for Occupied Buildings UNDER CONSTRUCTION).
Air measurements must be taken with the building is running under normal operations, but prior to occupancy.
|
|