During the site selection process, a project team gives preference to previously

[复制链接]

1759

主题

1

好友

5674

积分

管理员

Rank: 9Rank: 9Rank: 9

跳转到指定楼层
楼主
发表于 2012-8-4 17:13:07 |只看该作者 |倒序浏览
试卷: LEED AP ID+C 模拟试卷D[查看]
During the site selection process, a project team gives preference to previously developed urban sites that meet the density requirements for Sustainable Sites Credit, Development Density and Community Connectivity. What else will be required to earn this credit?
A: The space must be within 1/2 mile of 10 basic services
B: Pedestrian access must be provided between the building entrance and at least 10 basic services
C: The space must be within 1/4 mile of two different metro bus lines
D: The space must be in a community with a minimum density of 60,000 sq.ft. per acre net, in the correct density radius
E: The space must be located within 1/2 mile radius of a residential neighborhood with an average density of 10 units/ acre net

参考答案: D

本题解释:
Notes:

Reference: Sustainable Sites Credit, Development Density and Community Connectivity

The question asks how to qualify for the Development Density. Development Density is one of two options for Development Density and Community Connectivity.
Remember that even though the credit contains the names of both options, they are treated as seperately.

The question indicates the project will ‘...meet the density requirements for..’. You need to know when you that the terms ‘development density or density requirement’ it means Option 1 Development Density.

When you see ‘basic services’ or ‘average density of 10 units per acre net’ the question is asking about Option 2 Community Connectivity.

The requirements for Option 1 are ‘A building developed on a previously developed site. Select space in a building that is located in an established, walkable community with a minimum density of 60,000 sq. ft. per acre net (two-story downtown development)’.

Greenfield developments are not acceptable, so the project must be located on a previously developed site. This was given in the question.

Pedestrian access and proximity to basic services is required for Community Connectivity.
分享到: QQ空间QQ空间 腾讯微博腾讯微博 腾讯朋友腾讯朋友
分享分享0 收藏收藏0
回复

使用道具 举报

您需要登录后才可以回帖 登录 | 立即注册

关闭

站长推荐上一条 /1 下一条

Archiver|手机版|LEED GA/LEED AP考试学习平台|版权所有|备案号(沪ICP备11019119号-2)|leedgap   

GMT+8, 2024-12-23 14:23 , Processed in 0.074367 second(s), 25 queries .

Powered by Discuz! X2.5 & Exam 1.4

© 2001-2012 Comsenz Inc.

回顶部