A contractor will conduct a phased flush out of a building. The office building

[复制链接]

262

主题

0

好友

33

积分

管理员

Rank: 9Rank: 9Rank: 9

跳转到指定楼层
楼主
发表于 2012-8-3 09:23:20 |只看该作者 |倒序浏览
试卷: LEED AP ID+C 模拟试卷B[查看]
A contractor will conduct a phased flush out of a building. The office building is 75,000 SF. What volume of air is required for flush out before occupancy begins for Indoor Environmental Quality Credit, Construction Indoor Air Quality Management Plan-Before Occupancy?
A: 1,050,000,000 cubic feet
B: 262,500,000 cubic feet
C: 225,000,000 cubic feet
D: 787,500,000 cubic feet

参考答案: B

本题解释:
Reference: Indoor Environmental Quality Credit, Construction Indoor Air Quality Management Plan-Befo

For a phased occupancy the credit requires 3,500 cubic feet of air needed per square foot of building area before occupants can move and and the rest of the flush out continues untill each SF has had 14,000 cubic feet of air pass through.

75,000SF X 3,500 = 262,500,000 cubic feet needed before the occupancy can begin under this phased flush out plan.

Note that \'during construction\' can be confused with \'pre-occupancy\' because there are no occupants in the building. However these two terms describe different periods of time in construction as considered in the LEED rating system.
分享到: QQ空间QQ空间 腾讯微博腾讯微博 腾讯朋友腾讯朋友
分享分享0 收藏收藏0
回复

使用道具 举报

您需要登录后才可以回帖 登录 | 立即注册

关闭

站长推荐上一条 /1 下一条

Archiver|手机版|LEED GA/LEED AP考试学习平台|版权所有|备案号(沪ICP备11019119号-2)|leedgap   

GMT+8, 2025-4-6 02:46 , Processed in 0.077281 second(s), 25 queries .

Powered by Discuz! X2.5 & Exam 1.4

© 2001-2012 Comsenz Inc.

回顶部