A project area is 20,000 sf. The total segment area for the project is 100,000 s

[复制链接]

262

主题

0

好友

33

积分

管理员

Rank: 9Rank: 9Rank: 9

跳转到指定楼层
楼主
发表于 2012-7-29 22:19:53 |只看该作者 |倒序浏览
试卷: LEED AP ID+C 模拟试卷B[查看]
A project area is 20,000 sf. The total segment area for the project is 100,000 sf. The design energy cost of the HVAC system is $28,000. The baseline energy cost budget is $30,000. What is the percent reduction of annual HVAC energy use for the project?
A: 18%
B: 14%
C: 33%
D: 7%

参考答案: C

本题解释:
Reference: Energy and Atmosphere Credit, Optimize Energy Performance-HVAC, Calculations, Option 2, S

The formula is:

Reduction =
Baseline Energy Cost Budget - Design Case Energy Cost
Baseline Energy Cost Budget X (Project Area / Total Segment Area)

$30,000 - $28,000 = $2,000

Divide that by:
$30,000 X (20,000 sf / 100,000 sf) = $6,000

$2,000 / $6,000 = 33%

分享到: QQ空间QQ空间 腾讯微博腾讯微博 腾讯朋友腾讯朋友
分享分享0 收藏收藏0
回复

使用道具 举报

您需要登录后才可以回帖 登录 | 立即注册

关闭

站长推荐上一条 /1 下一条

Archiver|手机版|LEED GA/LEED AP考试学习平台|版权所有|备案号(沪ICP备11019119号-2)|leedgap   

GMT+8, 2024-12-23 09:46 , Processed in 0.076647 second(s), 25 queries .

Powered by Discuz! X2.5 & Exam 1.4

© 2001-2012 Comsenz Inc.

回顶部