A CxA has been selected to perform the fundamental commissioning of a bank. Whic

[复制链接]

1759

主题

1

好友

5674

积分

管理员

Rank: 9Rank: 9Rank: 9

跳转到指定楼层
楼主
发表于 2012-7-29 14:38:06 |只看该作者 |倒序浏览
试卷: LEED AP ID+C 模拟试卷A[查看]
A CxA has been selected to perform the fundamental commissioning of a bank. Which of the following must the CxA commission for LEED certification?(choose 2)
A: Gravity based water pump
B: Lighting and daylighting controls
C: Off-site renewable energy systems
D: Building envelope
E: HVAC

参考答案: BE

本题解释:
Reference: Energy and Atmosphere Prerequisite, Fundamental Commissioning of Building Energy Systems,

At a minimum the following energy-related systems must be commissioned:

HVAC
Lighting and daylighting controls
Domestic hot water systems
Renewable energy systems (wind, solar)

A gravity based water pump does not consume energy and would not need commissioning.

The building envelope is not one of the minimum systems for Fundamental Commissioning.
分享到: QQ空间QQ空间 腾讯微博腾讯微博 腾讯朋友腾讯朋友
分享分享0 收藏收藏0
回复

使用道具 举报

您需要登录后才可以回帖 登录 | 立即注册

关闭

站长推荐上一条 /1 下一条

Archiver|手机版|LEED GA/LEED AP考试学习平台|版权所有|备案号(沪ICP备11019119号-2)|leedgap   

GMT+8, 2024-12-23 09:49 , Processed in 0.076640 second(s), 25 queries .

Powered by Discuz! X2.5 & Exam 1.4

© 2001-2012 Comsenz Inc.

回顶部