For Enhanced Commissioning, when must the follow-up by the CxA be performed?

[复制链接]

203

主题

0

好友

512

积分

超级版主

Rank: 8Rank: 8

跳转到指定楼层
楼主
发表于 2012-8-28 19:44:51 |只看该作者 |倒序浏览
试卷: LEED AP BD+C模拟题D[查看]
For Enhanced Commissioning, when must the follow-up by the CxA be performed?
A: 10 months after LEED certification is awarded
B: 10 months after a certificate of occupancy is issued
C: 10 months after substantial completion
D: 10 months after occupancy

参考答案: C

本题解释:
Notes:
Reference: Energy and Atmosphere Credit, Enhanced Commissioning, Requirements
The CxA must be involved in reviewing the operation of the building with operations and
maintenance (O&M) staff and occupants within 10 months after substantial completion. A
plan for resolving outstanding commissioning-related issues must be included.
分享到: QQ空间QQ空间 腾讯微博腾讯微博 腾讯朋友腾讯朋友
分享分享0 收藏收藏0
回复

使用道具 举报

您需要登录后才可以回帖 登录 | 立即注册

关闭

站长推荐上一条 /1 下一条

Archiver|手机版|LEED GA/LEED AP考试学习平台|版权所有|备案号(沪ICP备11019119号-2)|leedgap   

GMT+8, 2024-12-28 05:14 , Processed in 0.074057 second(s), 25 queries .

Powered by Discuz! X2.5 & Exam 1.4

© 2001-2012 Comsenz Inc.

回顶部