试卷: LEED AP BD+C模拟题C[查看] A project building is 45,000 sq. ft. A project team has selected a commissioning agent who is a construction manager not holding any construction contracts. What will the agent not need to do for fundamental commissioning? A: Direct the commissioning team and the process B: Review results of system performance verification C: Coordinate commissioning testing D: Review building operation within 10 months of substantial completion 参考答案: D
本题解释: Notes:
The question asks what the agent will NOT need to do for fundamental commissioning.
Review the building operation within 10 months of substantial completion is part of enhanced commissioning, not fundamental
commissioning.
Energy and Atmosphere Credit, Enhanced Commissioning comes with an exemplary performance option. |
|