试卷: LEED AP BD+C模拟题A[查看] A project team working a new construction project is attempting to divert construction waste from
the landfill. Total construction waste is estimated to be 257 tons. What is the minimum number of
tons that need to be diverted to earn exemplary performance for Materials and Resources Credit,
Construction Waste Management? A: 245 tons B: 218 tons C: 257 tons D: 193 tons 参考答案: A
本题解释: Notes:
To earn exemplary performance for MR Credit 2, a project must divert 95% or more of total
construction waste.
If there is a total of 257 of construction waste, so 257*.95 = 244.15, round up
257 would also meet the requirement, but the question asks for the minimum number of tons, so
245 is the best choice. |
|