试卷: LEED AP ID+C 模拟试卷C[查看] What measures could be taken to achieve 40% treatment of a site area’s total phosphorous?
A: Removing all bioswales from parking lots B: Adding a constructed wetland C: Installing high albedo surfaces in the parking lot D: Planting trees to provide cover for hardscapes 参考答案: B
本题解释: This question refers to Sustainable Site Credit, Site Selection Option 2 Path 3: Stormwater Design - Quality Control
This credit requires the demonstration of reduction of Total Suspended Solids (TSS) and Total Phosphorus (TP)
A wetland, even one that is constructed, will help filtrate stormwater.
Trees are not a measure that is specified by LEED to treat storm water.
Bioswales should be added to parking lots, not removed.
The reflectivity of a surface does not impact stormwater. |
|