A 5 story office building is being constructed on the site of an old warehouse.

[复制链接]

203

主题

0

好友

512

积分

超级版主

Rank: 8Rank: 8

跳转到指定楼层
楼主
发表于 2012-8-12 18:42:55 |只看该作者 |正序浏览
试卷: LEED AP BD+C模拟题D[查看]
A 5 story office building is being constructed on the site of an old warehouse. The site has a zero-lot-line and is completely paved with non-porous pavement. The pre-development discharge volume of stormwater is 10,000 gallons. What post-development discharge volume would qualify for Sustainable Sites Credit, Stormwater Design-Quantity Control?
A: 8,000 gallons, or less
B: 10,000 gallons, or less
C: 5,000 gallons, or less
D: 7,500 gallons, or less

参考答案: D

本题解释:
Notes:
The site has an imperviousness greater than 50% because it is completely paved, so
Option 2 must be met for the requirements. A stormwater management plan must have a
25% decrease in volume. The pre-development discharge rate is 10,000 gallons, so the
post-development discharge rate must be 7,500 gallons or less (25% less than 10,000
gallons).
分享到: QQ空间QQ空间 腾讯微博腾讯微博 腾讯朋友腾讯朋友
分享分享0 收藏收藏0
回复

使用道具 举报

您需要登录后才可以回帖 登录 | 立即注册

关闭

站长推荐上一条 /1 下一条

Archiver|手机版|LEED GA/LEED AP考试学习平台|版权所有|备案号(沪ICP备11019119号-2)|leedgap   

GMT+8, 2024-12-26 10:27 , Processed in 0.088644 second(s), 26 queries .

Powered by Discuz! X2.5 & Exam 1.4

© 2001-2012 Comsenz Inc.

回顶部