试卷: LEED AP BD+C模拟题D[查看] For Enhanced Commissioning, when must the follow-up by the CxA be performed? A: 10 months after LEED certification is awarded B: 10 months after a certificate of occupancy is issued C: 10 months after substantial completion D: 10 months after occupancy 参考答案: C
本题解释: Notes:
Reference: Energy and Atmosphere Credit, Enhanced Commissioning, Requirements
The CxA must be involved in reviewing the operation of the building with operations and
maintenance (O&M) staff and occupants within 10 months after substantial completion. A
plan for resolving outstanding commissioning-related issues must be included. |
|