A new school project will have 1,000 students from grades 4-8 and 75 FTE staff.

[复制链接]

1759

主题

1

好友

5674

积分

管理员

Rank: 9Rank: 9Rank: 9

跳转到指定楼层
楼主
发表于 2012-8-12 16:22:18 |只看该作者 |倒序浏览
试卷: LEED AP BD+C模拟题A[查看]
A new school project will have 1,000 students from grades 4-8 and 75 FTE staff. What must the
project have to earn Sustainable Sites Credit, Alternative Transportation-Bicycle Storage and
Changing Rooms?(choose 2)
A: 5 shower and changing facilities
B: Dedicated bike lanes that extend at least to the end of the school property in 2 or more directions
C: 54 secure bicycle racks and/or storage
D: 4 shower and changing facilities

参考答案: BC

本题解释:
Notes:


Reference: Sustainable Sites Credit, Alternative Transportation-Bicycle Storage and Changing
Rooms, Requirements


For school projects, dedicated bike lanes that extend at least to the end of the school property in 2
or more directions are required


To calculate the number of secure bicycle spaces, multiply the total FTE staff occupants, peak
transients, and students by 0.05. In this example it was 1075 X 0.05 = 53.75 = 54 rounded up.


Showers are needed for FTE staff only. In this example it would be 75 FTE X 0.005 = 0.375 = 1
rounded up.
分享到: QQ空间QQ空间 腾讯微博腾讯微博 腾讯朋友腾讯朋友
分享分享0 收藏收藏0
回复

使用道具 举报

您需要登录后才可以回帖 登录 | 立即注册

关闭

站长推荐上一条 /1 下一条

Archiver|手机版|LEED GA/LEED AP考试学习平台|版权所有|备案号(沪ICP备11019119号-2)|leedgap   

GMT+8, 2024-12-25 23:26 , Processed in 0.080812 second(s), 26 queries .

Powered by Discuz! X2.5 & Exam 1.4

© 2001-2012 Comsenz Inc.

回顶部