A project building is 45,000 sq. ft. A project team has selected a commissioning agent who is a construction manager not holding any construction contracts. What will the agent not need to do for fundamental commissioning?
A: Direct the commissioning team and the process
B: Review results of system performance verification
C: Coordinate commissioning testing
D: Review building operation within 10 months of substantial completion

参考答案: D

本题解释:
Notes:
The question asks what the agent will NOT need to do for fundamental commissioning.
Review the building operation within 10 months of substantial completion is part of enhanced commissioning, not fundamental
commissioning.
Energy and Atmosphere Credit, Enhanced Commissioning comes with an exemplary performance option.
分享到: QQ空间QQ空间 腾讯微博腾讯微博 腾讯朋友腾讯朋友
分享分享0 收藏收藏0
回复

使用道具 举报

您需要登录后才可以回帖 登录 | 立即注册

关闭

站长推荐上一条 /1 下一条

Archiver|手机版|LEED GA/LEED AP考试学习平台|版权所有|备案号(沪ICP备11019119号-2)|leedgap   

GMT+8, 2024-12-27 12:47 , Processed in 0.080569 second(s), 26 queries .

Powered by Discuz! X2.5 & Exam 1.4

© 2001-2012 Comsenz Inc.

回顶部