A new retail project has a baseline building energy cost of $87,256. The propose

[复制链接]

1759

主题

1

好友

5674

积分

管理员

Rank: 9Rank: 9Rank: 9

跳转到指定楼层
楼主
发表于 2012-8-12 18:42:55 |只看该作者 |倒序浏览
试卷: LEED AP BD+C模拟题C[查看]
A new retail project has a baseline building energy cost of $87,256. The proposed building energy cost is $69,744. What is the default process energy cost of the building?
A: $17,436
B: $21,814
C: $17,512
D: $4,378

参考答案: B

本题解释:
Notes:
Reference: Energy And Atmosphere Prerequisite 2 Minimum Energy Performance, Requirements
Process energy is used in the whole building energy simulation to determine the annual energy cost calculated for a proposed design.
By default the value is 25% of the total energy cost for the baseline building. A value less than 25% can be used if documentation can be
provided.
$87,256 baseline X 25% = $21,814
分享到: QQ空间QQ空间 腾讯微博腾讯微博 腾讯朋友腾讯朋友
分享分享0 收藏收藏0
回复

使用道具 举报

您需要登录后才可以回帖 登录 | 立即注册

关闭

站长推荐上一条 /1 下一条

Archiver|手机版|LEED GA/LEED AP考试学习平台|版权所有|备案号(沪ICP备11019119号-2)|leedgap   

GMT+8, 2024-12-27 13:33 , Processed in 0.079150 second(s), 25 queries .

Powered by Discuz! X2.5 & Exam 1.4

© 2001-2012 Comsenz Inc.

回顶部