LEED GAP

 找回密码
 立即注册

QQ登录

只需一步,快速开始

搜索
查看: 248|回复: 0
打印 上一主题 下一主题

A project moved beyond the design phase before a green-building consultant was a

[复制链接]

1759

主题

1

好友

5674

积分

管理员

Rank: 9Rank: 9Rank: 9

跳转到指定楼层
楼主
发表于 2012-8-12 16:22:18 |只看该作者 |倒序浏览
试卷: LEED AP BD+C模拟题A[查看]
A project moved beyond the design phase before a green-building consultant was asked to join the
project team. The building owner wants to hear about design strategies that can have minimal
impact on the project budget. The design consultant suggests using light-colored pervious paving
in lieu of a black asphalt parking lot. What credits would this design strategy contribute toward?(choose 2)
A: Sustainable Sites Credit, Stormwater Design-Quantity Control
B: Sustainable Sites Credit, Stormwater Design-Quality Control
C: Sustainable Sites Credit, Light Pollution Reduction
D: Sustainable Sites Credit, Heat Island Effect-Roof

参考答案: AB

本题解释:
Notes:


The pervious pavement choice will help with both the quantity and quality of stormwater.


The light- colored paving would also help earn Heat Island Effect, Non-Roof (which was
intentionally not given as an answer choice in order to help you learn the not-so-obvious answers).
分享到: QQ空间QQ空间 腾讯微博腾讯微博 腾讯朋友腾讯朋友
分享分享0 收藏收藏0
回复

使用道具 举报

您需要登录后才可以回帖 登录 | 立即注册

关闭

站长推荐上一条 /1 下一条

Archiver|手机版|LEED GA/LEED AP考试学习平台|版权所有|备案号(沪ICP备11019119号-2)|leedgap   

GMT+8, 2024-12-26 22:55 , Processed in 0.076957 second(s), 25 queries .

Powered by Discuz! X2.5 & Exam 1.4

© 2001-2012 Comsenz Inc.

回顶部