A residential building will include a common laundry room, postal area, and heat

[复制链接]

1759

主题

1

好友

5674

积分

管理员

Rank: 9Rank: 9Rank: 9

跳转到指定楼层
楼主
发表于 2012-8-12 16:22:18 |只看该作者 |倒序浏览
试卷: LEED AP BD+C模拟题A[查看]
A residential building will include a common laundry room, postal area, and heated swimming
pool. An independent CxA has been hired to help the project achieve Energy and Atmosphere
Credit, Enhanced Commissioning. What additional activities will the CxA be required to complete
beyond the requirements of fundamental commissioning?(choose 2)
A: Develop a systems manual for the heated swimming pool
B: Review contractor submittals applicable to the heated swimming pool
C: Implement the commissioning plan
D: Commissioning design review prior to mid-construction docs
E: Verify that requirements for training are completed

参考答案: BD

本题解释:
Notes:


There are several responsibilities only the CxA can complete for Enhanced Commissioning. Some
items can be completed by the CxA or other members of the project team (see Table 1 of
Fundamental Commissioning). The question specifically asks for items that the CxA is required to
perform. So the correct answers can only be performed by the CxA.
分享到: QQ空间QQ空间 腾讯微博腾讯微博 腾讯朋友腾讯朋友
分享分享0 收藏收藏0
回复

使用道具 举报

您需要登录后才可以回帖 登录 | 立即注册

关闭

站长推荐上一条 /1 下一条

Archiver|手机版|LEED GA/LEED AP考试学习平台|版权所有|备案号(沪ICP备11019119号-2)|leedgap   

GMT+8, 2024-12-26 23:22 , Processed in 0.076494 second(s), 25 queries .

Powered by Discuz! X2.5 & Exam 1.4

© 2001-2012 Comsenz Inc.

回顶部