- 注册时间
- 2012-6-6
- 最后登录
- 2024-12-11
- 阅读权限
- 200
- 积分
- 5674
- 精华
- 3
- 帖子
- 1765
|
试卷: LEED AP BD+C模拟题A[查看] After the design phase of a school project the team decided to replace outdoor basketball courts
with an athletic field covered in turf grass. What statement is true regarding this design change? A: The field may be included in Water Efficient Landscaping calculations B: The field would not contribute to joint use of facilities C: The field will require curfew timers for the lighting that shutoff no later than 10 p.m. D: The field will not contribute to maximizing open space 参考答案: A
本题解释: Notes:
Reference: Water Efficiency Credit, Water-Efficient Landscaping, Implementation, Technologies
For school projects the playing fields can be included in the water calculations at the project teams
discretion. They are not required.
The field could be used for joint-use.
Curfew timers must turn off no later than 11 p.m., not 10 p.m.
Playing fields can contribute to open space |
|