试卷: LEED AP BD+C模拟题A[查看] A civil engineer is working with the project team to finalize a construction activity stormwater
pollution prevention plan. What must be included in this plan? A: Quantity of total suspended solids removed B: Stormwater harvesting measurements C: Pre and post stormwater discharge rates D: All measures to prevent stormwater contamination,lsedimentation,erosion during construction comply with Clean Water Act 参考答案: D
本题解释: Notes:
Reference: Sustainable Sites Prerequisite, Construction Activity Pollution Prevention, Definitions
A stormwater pollution prevention plan is part of construction activity pollution prevention (not
SS 6 Stormwater Design). The plan must include all measures to prevent stormwater
contamination, control sedimentation and erosion during construction, and comply with the
requirements of the Clean Water Act |
|