试卷: LEED AP BD+C模拟题A[查看] A school project will include a natatorium. What must be done to prevent mold in the project? A: Demonstrate compliance with the Typical Natatorium Design Conditions of the ASHRAE HVAC Applications Handbook, 2003 B: Conduct a thermal comfort survey 12 months after occupancy C: Limit relative humidity to 60% or less, only during occupied hours D: Install MERV 13 air filters 参考答案: A
本题解释: Notes:
Reference: Indoor Environmental Quality Credit, Mold Prevention, Requirements
For Mold Prevention in a school projects must achieve credits:
IEQ C3.1 IAQ Management Plan During Construction
IEQ 7.1 and 7.2 Thermal Comfort Design and Verification
If a school project includes a natatorium, for IEQ 7.1 the project must demonstrate compliance
with the Typical Natatorium Design Conditions of the ASHRAE HVAC Applications Handbook,
2003.
For Mold Prevention relative humidity must be limited to 60% or less during all load conditions,
both occupied and unoccupied. |
|