试卷: LEED AP BD+C模拟题A[查看] A building contractor is finalizing the tasks that must be complete before a building flush-out
begins. What task does not have to be completed prior to a building flush-out? A: Commissioning B: Installation of all carpet C: Installation of all furnishings D: Cleaning 参考答案: A
本题解释: Reference: Indoor Environmental Quality Credit, Construction Indoor Air Quality Management
Plan-Before Occupancy, Implementation
Commissioning can take place during the flush-out if no additional contaminants are introduced.
Commissioning can also take place after the flush out.
Cleaning, punch-list items, and the installation of furniture and furnishings (see Timeline and
Team) must be done prior to the flush-out. |
|