A general contractor is working on documenting the quantity of materials reuse for a project. If a
salvaged material came from on-site, how will the contractor determine the replacement value of
the material?
A: Using a comparable material in the local market, including labor and shipping
B: An estimate based on the contractor’ s knowledge of material prices
C: Using a comparable material in the local market, excluding labor and shipping
D: Using a comparable material in the local market and multiplying it by 45%

参考答案: C

本题解释:
Notes:
Reference: Materials and Resources Credit, Materials Reuse, Calculations
Material reuse is based on the total cost of the materials and the total cost of any reused/salvaged
materials.
If a salvaged material came from on-site, the replacement value of the material is determined by
comparing the material to something available in the local market. Labor and shipping are
excluded, as are any discounts the seller may apply.
分享到: QQ空间QQ空间 腾讯微博腾讯微博 腾讯朋友腾讯朋友
分享分享0 收藏收藏0
回复

使用道具 举报

您需要登录后才可以回帖 登录 | 立即注册

关闭

站长推荐上一条 /1 下一条

Archiver|手机版|LEED GA/LEED AP考试学习平台|版权所有|备案号(沪ICP备11019119号-2)|leedgap   

GMT+8, 2024-12-26 11:05 , Processed in 0.079366 second(s), 25 queries .

Powered by Discuz! X2.5 & Exam 1.4

© 2001-2012 Comsenz Inc.

回顶部