试卷: LEED AP BD+C模拟题A[查看] A museum is closing down for a period of time while some major renovations occur, and a new
addition is added to the building. What housekeeping tasks must be completed to meet SMACNA
requirements for the IAQ management plan during construction? A: Clean the project site at least every 24 hours when construction has taken place B: Using wetting agents for dust C: Ventilate the construction area at least weekly with outside air D: Store all porous building materials outside of the construction area until they are needed 参考答案: B
本题解释: Reference: Indoor Environmental Quality Credit, Construction Indoor Air Quality Management
Plan-During Construction, Implementation, Housekeeping
Using wetting agents for dust is recommended for housekeeping as well as using high efficiency
particulate filters in vacuum cleaners.
Ventilating the construction area helps with Pathway Interruption, not Housekeeping.
While the project must be kept clean more frequently than normal, no specified time period (such
as every 24 hours) is specified.
Porous building materials need to be stored and protected from moisture damage, but they do not
have to be stored outside of the construction area. They should be kept where there are low
humidity levels and protected from water. |
|