试卷: LEED AP ID+C 模拟试卷C[查看]
The commissioning authority has the majority of responsibilities in enhanced commissioning. What responsibilities can other members of the team assist with?

A: Review building operation within 10 months with O&M staff and occupants. Include plans for resolution of issues
B: Commissioning design review of the owner’s project requirements, basis of design and design documents
C: Update the basis of design during design and construction
D: Review of contractor submittals applicable to systems being commissioned
E: Prior to the construction document phase, review the completion of all commissioning process activities

参考答案: C

本题解释:
See EA Prerequisite 1, Table 2
Note the differences between what tasks are allowed to be performed by which parties.
分享到: QQ空间QQ空间 腾讯微博腾讯微博 腾讯朋友腾讯朋友
分享分享0 收藏收藏0
回复

使用道具 举报

您需要登录后才可以回帖 登录 | 立即注册

关闭

站长推荐上一条 /1 下一条

Archiver|手机版|LEED GA/LEED AP考试学习平台|版权所有|备案号(沪ICP备11019119号-2)|leedgap   

GMT+8, 2024-12-24 03:38 , Processed in 0.076232 second(s), 25 queries .

Powered by Discuz! X2.5 & Exam 1.4

© 2001-2012 Comsenz Inc.

回顶部