试卷: LEED AP ID+C 模拟试卷C[查看] A contractor will try to meet the SMACNA guidelines for Indoor Environmental Quality Credit, Construction Indoor Air Quality Management Plan-During Construction. What aspects does the contractor need to document to achieve this credit?(choose 2) A: A building flushout with a total air volume of 14,000 cu. ft. per sq. ft. per floor was used B: MERV 8 filtration media was used for permanently installed air handlers C: On-site absorptive materials were protected from moisture damage D: On-site absorptive materials were protected from moisture damage 参考答案: BC
本题解释: Reference: Indoor Environmental Quality Credit, Construction Indoor Air Quality Management Plan-Duri
For this credit:
-Meet SMACNA guidelines
-Protect absorptive material (stored and installed) from moisture damage
-Use MERV 8 filters for permanent air handlers
A building flushout is not required for this credit, but is required for IAQ Management Plan - Before Occupancy.
|
|