试卷: LEED AP ID+C 模拟试卷C[查看] A project team has followed the requirements of the Advanced Building’s Core Performance Guide to help reduce energy use and operating costs. Some extra space in an office layout is being considered for a 2,600 SF training room. What will need to be done for the project to earn 10 points for Energy and Atmosphere Credit, Optimize Energy Performance-HVAC? A: A space control device must be installed that turns the temperature down after 30 minutes of inactivity in the space B: The space must meet lighting density standards C: The space must be separately zoned D: The space must include at least 2 controls 参考答案: C
本题解释: Energy and Atmosphere Credit, Optimize Energy Performance-HVAC
Since the Advanced Building’s Core Performance Guide is being followed, Option 1 is being used. Following this standard will help earn 5 points for the project. To earn an additional 5 points for a total of 10 points, HVAC systems must be separately zoned. |
|