试卷: LEED AP ID+C 模拟试卷C[查看] A building contractor and owner have discussed doing an occupied flushout in order to move some of the owner’s employees into a new office space. What would the contractor not do as part of an occupied flushout? A: Begin the minimum ventilation rate at least three hours prior to daily occupancy B: Continue the minimum ventilation rate while the space is occupied C: Keep relative humidity above 60% D: Keep occupants out until 3,500 cu. ft. of air per square foot has been replaced 参考答案: C
本题解释: Reference: Indoor Environmental Quality Credit, Construction Indoor Air Quality Management Plan
The relative humidity should be below 60%, not above
|
|