A project takes up 68,000 SF of a 125,000 SF building. The project will have 325

[复制链接]

262

主题

0

好友

33

积分

管理员

Rank: 9Rank: 9Rank: 9

跳转到指定楼层
楼主
发表于 2012-8-4 18:31:42 |只看该作者 |倒序浏览
试卷: LEED AP ID+C 模拟试卷C[查看]
A project takes up 68,000 SF of a 125,000 SF building. The project will have 325 FTEs and 350 part-time employees. The project team already has 15 parking spaces reserved for carpools. How many more must be set aside to earn Sustainable Sites, Alternative Transportation - Parking Availability?

A: 25
B: -0-
C: 10
D: 15

参考答案: B

本题解释:
See Sustainable Sites, Alternative Transportation - Parking Availability, Calculations
The project only needs to provide 13 parking spaces so no more are needed.

325 FTEs + (350 Part Time Workers X 0.5) = 500 FTEs

500 X 5% = 25

25 / 2 (minimum 2 people per car) = 12.5, round up for 13
分享到: QQ空间QQ空间 腾讯微博腾讯微博 腾讯朋友腾讯朋友
分享分享0 收藏收藏0
回复

使用道具 举报

您需要登录后才可以回帖 登录 | 立即注册

关闭

站长推荐上一条 /1 下一条

Archiver|手机版|LEED GA/LEED AP考试学习平台|版权所有|备案号(沪ICP备11019119号-2)|leedgap   

GMT+8, 2024-12-24 04:19 , Processed in 0.077536 second(s), 25 queries .

Powered by Discuz! X2.5 & Exam 1.4

© 2001-2012 Comsenz Inc.

回顶部