试卷: LEED AP ID+C 模拟试卷B[查看] A CxA has arrived on a project site to verify the installation and performance of the systems as part of fundamental commissioning. Which of the following are not typical steps the CxA will perform?
A: Prefunctional inspections B: Functional performance testing C: Comparing results with the owner’s project requirements D: Training operating personnel 参考答案: D
本题解释: Reference: Energy and Atmosphere Prerequisite, Fundamental Commissioning of Building Energy Systems,
Not the question uses the word NOT.
When verifying the installation and performance of commissioned systems, three steps are typical.
1. Installation inspections
2. System performance testing
3. Comparison of the results to the original requirements
|
|