LEED GAP

 找回密码
 立即注册

QQ登录

只需一步,快速开始

搜索
查看: 1028|回复: 0
打印 上一主题 下一主题

The owner of a new oceanfront museum project wants to use 35% green power, but t

[复制链接]

1759

主题

1

好友

5674

积分

管理员

Rank: 9Rank: 9Rank: 9

跳转到指定楼层
楼主
发表于 2012-8-28 19:44:51 |只看该作者 |倒序浏览
试卷: LEED AP BD+C模拟题C[查看]
The owner of a new oceanfront museum project wants to use 35% green power, but the direct purchase of Green-e certified power is not available through the local utilities. An energy model was not done for Energy and Atmosphere Credit, Optimize Energy Performance. What information is not required when determining the quantity of Tradable Renewable Certificates to purchase?
A: Emissions criteria for the non-renewable portion of the electricity
B: Building type
C: Total building area (sq. ft.)
D: Median electrical intensity (kWh/sf-yr)

参考答案: A

本题解释:
Notes:
The question asks what information will not be required. Emissions criteria would not be used.
The CBECS database uses the building type and total building area to determine the default electricity consumption.
The median electrical intensity will be used to determine the required green power quantity.
分享到: QQ空间QQ空间 腾讯微博腾讯微博 腾讯朋友腾讯朋友
分享分享0 收藏收藏0
回复

使用道具 举报

您需要登录后才可以回帖 登录 | 立即注册

关闭

站长推荐上一条 /1 下一条

Archiver|手机版|LEED GA/LEED AP考试学习平台|版权所有|备案号(沪ICP备11019119号-2)|leedgap   

GMT+8, 2024-12-23 00:30 , Processed in 0.080867 second(s), 25 queries .

Powered by Discuz! X2.5 & Exam 1.4

© 2001-2012 Comsenz Inc.

回顶部