试卷: LEED AP ID+C 模拟试卷A[查看] The baseline case imperviousness for a project site is 95%. An office renovation will have site improvements to an existing asphalt pavement parking lot. The size of the parking lot is 26,134 sf. The design case materials that will be used as replacement include:
Surface ; Runoff Coefficient ; Area (sf)
Asphalt Pavement ; 0.95 ; 7,678;
Pervious Pavement ; 0.65 ; 5,086;
Vegetation, Flat ; 0.10 ; 13,370;
What is the reduction in imperviousness from the new design? A: 50% B: 41% C: 43% D: 54% 参考答案: B
本题解释: Reference: Sustainable Sites Credit, Site Selection, Stormwater Design-Quantity Control, Calculation
Multiply each surface by the runoff coefficient to calculate the total impervious area.
Surface Runoff Coefficient Area (sf) Impervious Area (sf)
----------------------------------------------------------------------------
Asphalt Pavement 0.95 7,678 7,294
Pervious Pavement 0.65 5,086 3,306
Vegetation, Flat 0.10 13,370 1,337
Total area: 26,134 sf
Total impervious area: 11,937 sf (add up all 3 columns of surfaces)
Imperviousness = total pervious area (sf) / total site area (sf)
(26,134 - 11,937) / 26,134 = 54% impervious
The baseline case had an imperviousness of 95% (stated in the question) resulting in a reduction of 41%.
Since the reduction is 41%, and the baseline case is 95%, we can calculate that the design case is 54%.
95% baseline case - 54% design case = 41% |
|