- 注册时间
- 2012-6-6
- 最后登录
- 2025-4-16
- 阅读权限
- 200
- 积分
- 5680
- 精华
- 3
- 帖子
- 1765
  
|
试卷: LEED AP BD+C模拟题C[查看] A CxA has been selected who is a subcontractor of the general contractor with construction responsibilities. What tasks do not need to be performed for fundamental commissioning? A: Review the basis of design B: Complete a summary commissioning report C: Develop and incorporate commissioning requirements into the construction documents D: Develop a systems manual 参考答案: D
本题解释: Notes:
Reference: Energy and Atmosphere Prerequisite, Fundamental Commissioning of Building Energy Systems
The question asks for something that does not need to be done for fundamental commissioning. Developing a systems manual is part of
Enhanced Commissioning, not Fundamental Commissioning.
There are six activities that must be completed by the project team for Fundamental Commissioning.
1. Designate an individual as the commissioning authority (CxA) to lead, review and oversee the completion of the commissioning process
activities.
2. The owner must document the owner\'s project requirements. The design team must develop the basis of design. The CxA must review
these documents for clarity and completeness. The owner and design team must be responsible for updates to their respective documents.
3. Develop and incorporate commissioning requirements into the construction documents.
4. Develop and implement a commissioning plan.
5. Verify the installation and performance of the systems to be commissioned.
6. Complete a summary commissioning report. |
|