试卷: LEED AP BD+C模拟题B[查看] A major renovation of a 30,000 sq. ft. dormitory on a college campus will include removing
fill dirt and contouring the land to prevent water damage to the building foundation. Which
of the following is required to achieve Sustainable Sites Prerequisite, Construction
Activity Pollution Prevention? A: Confirmation that the project complies with NPDES or local regulations if more stringent B: Landscape architect sign off on all pollution prevention actions C: Best Management Practices (BMP) plan D: Making sure the post-development runoff rate does not exceed the pre-development runoff rate 参考答案: A
本题解释: Notes:
Reference: Sustainable Sites Prerequisite, Construction Activity Pollution Prevention,
Requirements |
|