试卷: LEED AP BD+C模拟题C[查看] A new construction project team is putting together a project timeline for tasks that must be completed after construction. To account for energy consumption over time what is the minimum amount of time the M&V period must cover? A: 12 months beginning after fundamental commissioning B: 12 months beginning after occupancy C: 12 months beginning after LEED certification D: 12 months after substantial completion 参考答案: B
本题解释: Notes:
The M&V period must cover a period of no less than one year of post-construction occupancy.
The other period relative to LEED NC is enhanced commissioning, which occurs within 10 months after substantial completion. |
|