试卷: LEED AP BD+C模拟题D[查看] A major renovation of a 30,000 sq. ft. dormitory on a college campus will include removing
fill dirt and contouring the land to prevent water damage to the building foundation. Which
of the following is required to achieve Sustainable Sites Prerequisite, Construction Activity
Pollution Prevention? A: Confirmation that the project complies with NPDES or local regulations if more stringent B: Best Management Practices (BMP) plan C: Landscape architect sign off on all pollution prevention actions D: Making sure the post-development runoff rate does not exceed the pre-development runoff rate 参考答案: A
本题解释: Notes:
Reference: Sustainable Sites Prerequisite, Construction Activity Pollution Prevention,
Requirements
The project must comply with the more stringent of NPDES or local regulations. |
|