试卷: LEED AP BD+C模拟题D[查看] For projects that will record indoor light measurements to determine daylight illumination
levels, what must the project team include in the design? A: Daylight redirection and/or glare control devices B: Sunlight redirection C: View-preserving automated shades D: Increased glazing 参考答案: A
本题解释: Notes:
Reference: Indoor Environmental Quality Credit, Daylight and Views-Daylight ,
Requirements, Option 3
Glare control or daylight redirection is required because it can hinder visual tasks in high
contrast situations.
The only exceptions are areas where tasks are performed that could be hindered by
daylight, but the team will have to explain why these areas are excluded. |
|