试卷: LEED AP BD+C模拟题A[查看] A residential building will include a common laundry room, postal area, and heated swimming
pool. An independent CxA has been hired to help the project achieve Energy and Atmosphere
Credit, Enhanced Commissioning. What additional activities will the CxA be required to complete
beyond the requirements of fundamental commissioning?(choose 2) A: Develop a systems manual for the heated swimming pool B: Review contractor submittals applicable to the heated swimming pool C: Implement the commissioning plan D: Commissioning design review prior to mid-construction docs E: Verify that requirements for training are completed 参考答案: BD
本题解释: Notes:
There are several responsibilities only the CxA can complete for Enhanced Commissioning. Some
items can be completed by the CxA or other members of the project team (see Table 1 of
Fundamental Commissioning). The question specifically asks for items that the CxA is required to
perform. So the correct answers can only be performed by the CxA. |
|