试卷: LEED AP BD+C模拟题A[查看] A project site is chosen in a rural area. In the charrette the project team is discussing the option of
including a packaged biological wastewater treatment system to treat 100% wastewater on-site to
tertiary standards. What is true about the decision to include one of these systems?(choose 2) A: Public infrastructure costs would be reduced B: The recycled water could not be used for fountains in the landscape C: The project may earn 3 points for this decision D: Building energy costs would be decreased 参考答案: AC
本题解释: Notes:
Reference: Water Efficiency Credit, Innovative Wastewater Technologies
The project would earn 2 points for Water Efficiency Credit, Innovative Wastewater Technologies
and 1 point under ID for treating 100% of wastewater on-site to tertiary standards.
One issue with packaged biological wastewater system to treat wastewater onsite is they have high
initial costs.
Building energy costs would increase because these types of systems require energy to run.
Public infrastructure would be reduced to the rural area because the sewage drains would not need
to be run to the site. However it is possible the city may require the sewage lines to be installed
anyway.
The water could be used in the landscape. Tertiary treatment, or advanced treatment, removes
specific residual substances, trace organic materials, nutrients, and other constituents that are not
removed by biological processes. Tertiary-treated recycled water is safe for all human contact,
except drinking. |
|