试卷: LEED v4 ID+C模拟题A卷英文[查看] A project team for a retail project is conducting a waste stream study over a 24-hour period to track the waste generated. What does the project team need to identify for the audit as part of MR Prerequisite Storage and Collection of Recyclables? A: All waste streams accepted by a waste hauler B: The top four recyclable waste streams by volume C: The top five recyclable waste streams by weight or volume D: All waste streams that make up more than 10% of the total waste by volume 参考答案: C
本题解释: Note C: Retail projects must identify the top five recyclable waste streams by either weight or volume.