试卷: LEED AP ID+C 模拟试卷C[查看]
A contractor will try to meet the SMACNA guidelines for Indoor Environmental Quality Credit, Construction Indoor Air Quality Management Plan-During Construction. What aspects does the contractor need to document to achieve this credit?(choose 2)
A: A building flushout with a total air volume of 14,000 cu. ft. per sq. ft. per floor was used
B: MERV 8 filtration media was used for permanently installed air handlers
C: On-site absorptive materials were protected from moisture damage
D: On-site absorptive materials were protected from moisture damage

参考答案: BC

本题解释:
Reference: Indoor Environmental Quality Credit, Construction Indoor Air Quality Management Plan-Duri

For this credit:

-Meet SMACNA guidelines
-Protect absorptive material (stored and installed) from moisture damage
-Use MERV 8 filters for permanent air handlers

A building flushout is not required for this credit, but is required for IAQ Management Plan - Before Occupancy.
分享到: QQ空间QQ空间 腾讯微博腾讯微博 腾讯朋友腾讯朋友
分享分享0 收藏收藏0
回复

使用道具 举报

您需要登录后才可以回帖 登录 | 立即注册

关闭

站长推荐上一条 /1 下一条

Archiver|手机版|LEED GA/LEED AP考试学习平台|版权所有|备案号(沪ICP备11019119号-2)|leedgap   

GMT+8, 2024-12-23 22:47 , Processed in 0.073728 second(s), 26 queries .

Powered by Discuz! X2.5 & Exam 1.4

© 2001-2012 Comsenz Inc.

回顶部