试卷: LEED AP ID+C 模拟试卷D[查看] An office relocation project fell behind schedule and the building flush out will need to occur while the occupants are in the office. When must the flush-out period occur if the occupants are in the office?
A: At the start of occupancy each day, continuing until the last person leaves the building each day B: After the occupants leave each day, continuing until they arrive they next day C: 24 hours prior to occupancy D: 3 hours prior to occupancy and continue during occupancy 参考答案: D
本题解释: Notes:
Reference: Indoor Environmental Quality Credit, Construction Indoor Air Quality Management Plan-Befo
For an occupied flush-out the flush-out must begin 3 hours prior to occupancy and continue during occupancy. Occupancy cannot begin until at least 3,500 cu. ft. outside air / sq. ft. of floor area has been introduced. |
|